PROJECT INFORMATION
Beddington to Sutton – 132kV Cable Infrastructure
Client Name
UK Power Networks (UKPN)
Principal Contractor
Kier Group
Scope
Civil Engineering & Infrastructure Support
Project Overview
NVM supported the delivery of a major 132kV infrastructure project between Beddington and Sutton, providing civil engineering and excavation works along a complex cable route.
Operating within a highly congested urban environment, the project presented significant challenges in terms of access, ground conditions, and coordination with ongoing works. Despite these constraints, NVM successfully delivered approximately 3.5 km of trench excavation, along with backfilling and preparation for final reinstatement.
The wider project included substation works, tunnelling operations, cable installation, and construction of joint bays, forming part of a major investment in energy infrastructure.
NVM’s role focused on the safe and efficient execution of trenching and civil works, contributing to the successful progression of the overall programme.
Works Delivered
Excavation for 132kV dual circuit cable route
Trench installation (approx. 1.2m depth / 1.1m width)
Delivery of approximately 3.5 km of trench excavation
Backfilling and preparation for reinstatement
Support with cable route infrastructure
Civil works within congested urban environment